How To Plan A PVC Production Line For Small And Mid-Size Factories

Nov 12, 2026 Leave a message



Most PVC lines get bought twice: once at the quoted price, and again on everything that price left out. Here is the order we would plan in, if it were our own money.

4,800 h

Realistic running hours a year

65 mm

Where most strip lines start

15–20%

Of budget is working capital


A curtain strip line and a rigid sheet line are not the same animal, and neither is a 300-tonne plan and a 900-tonne one. What follows is the sequence we walk through with buyers before a single machine is specified, including the parts that never appear on a quotation.

 


 

01 / OUTPUT FIRST

The product decides the line, not the other way round

 

          ◆Curtain strip, 200 mm wide, 1–3 mm.Single screw, sheet die, haul-off, winder. Calendering is not a serious option under about 600 kg/h.


         ◆ Rigid sheet, 1–6 mm.Twin screw or single screw plus a three-roll calender. Different budget, different footprint, different operator skill.


         ◆Food wrap. Line cleanliness, migration compliance, and film tolerance decide the screw and the additive package long before output does.

 

So write the spec first: width, thickness range, colour, surface finish, roll size, packing. A line sized around a vague "PVC sheet" gets rebuilt within two years, and the rebuild costs more than the original machine.

 


 

02 / CAPACITY

Work backwards from tonnage, not from nameplate output

 

Nameplate figures are measured on a good day, with a warm die and a compound the factory already knows. Plan with effective hours instead.

kg/h needed = annual tonnes × 1,000 ÷ (days × shifts × hours × 0.80)

 

Target output             kg/h needed              Typical configuration



150 t / year                    31                                     45 mm single screw, manual winder 



300 t / year                    63                                     55–65 mm single screw, semi-automatic 



600 t / year                   125                                   65–75 mm, automatic winding, second die 



1,200 t / year               250                                   80 mm twin screw with calender, full automation 


Based on 300 working days, two 10-hour shifts, 80% uptime. Uptime is where plans fail: budget 80%, never 95%.


 

 03 / THE SITE

Floor, power, water and air decide more than the extruder

 

We are called into more buildings than boardrooms. Half the delays we see are concrete and copper, not machinery.

 

Table 02 - Site requirements for a 65 mm line

 

Item                                Rule of thumb                                               Why it bites 



Clear run                       8 m straight, die to winder                         Turning a warm strip 4 m out gives you permanent curl 



Floor area                    150–250 m² with resin storage                  Cheaper to rent 50 m² more than to move a line later 



Installed load             60–90 kW                                                            Transformer sized at 1.5× installed, or the first cold start trips the plant 



Cooling water            3–5 m³/h circulating, 5–10 HP chiller     Warm water in July shows up as dimensional drift, not as a fault 



Compressed air        0.6 m³/min at 0.7 MPa, dried                      Wet air destroys cylinders and solenoid valves within a season 



Ceiling height            4.5–5 m at the hopper                                   Dryer plus loader stack; nobody measures this until the crane arrives 


 

 04 / COMPOUND

Two identical lines, two compounds, two different businesses

 

The machine is a pump and a heater. What comes out of it is decided by the formulation, and the formulation is decided by where you sell.

 

           ◆Stabilizer. Lead-based is cheap and still permitted in some markets. Ca/Zn or tin is what EU and US buyers accept. Choose by destination, not by price per kilogram.


           ◆Filler.20–40 phr calcium carbonate cuts cost and adds stiffness. Past 50 phr, you are selling chalk with a straight face, and the customer finds out in month three.


           ◆Plasticizer.30–60 phr for flexible strip. The strip that cracked in a Canadian January was a plasticizer question, not a machine question.

Ask any supplier for the starting formulation and a trial report before you sign. If the answer is "our engineer will handle it on site", you have bought a machine and rented a hope.

 


 

05 / BUDGET

Where the money actually goes

 

Item                                                                    Share of project       Note 



Extruder, die, downstream                        45–55%                          The part every buyer negotiates hardest 



Mixer, compound prep                               10–15%                           Skipped most often; reappears as thickness drift 



Chiller, air, transformer                              8–12%                             Local contractor, usually underestimated 



Freight, installation, commissioning    8–12%                            One 40HQ, flights, 10–14 days on site 



Spare screw, die, wear parts                    5–8%                               Cheaper than a two-week shutdown 



Working capital, 60–90 days                    15–20%                          Resin before the first invoice is paid 



The machine is the cheap part.
Compound, power supply, and ninety days of raw material are what decide whether the line makes money. Projects we are asked to rescue were almost always under-budgeted here, not over-built there.

 


 

06 / ACCEPTANCE

What to test before you release the balance

 

Test                                                               Pass mark 



Output at rated thickness                    Within 5% of quoted kg/h, held for 4 consecutive hours 



Thickness across the width                ±5%, measured at five points, not just the middle 



Energy per kilogram                               Record kWh/kg. It is the only number you can compare between suppliers 



Scrap on the first shift                           Under 8%, and falling by the end of the week 



Changeover to a second die               Under 4 hours, done by your own crew, not the installer's 


 

Five things that should end a conversation early:

 

       ╳No die drawing before the deposit, only photographs of a similar machine


       ╳"Formula included" with no written formulation and no trial report


       ╳Commissioning by video call, with no engineer on site


       ╳A price per set that quietly excludes haul-off, chiller, or electrical panel


       ╳A delivery date that ignores Spring Festival, then slips six weeks

 



Send us the product spec, the target tonnage, and a photograph of your power supply. We will come back with a line configuration, a compound starting point, and the site requirements, before anyone mentions price.